Defining work schedule and visible week/day time limits in Gantt Chart Light Library

How can I define a specific work schedule and/or limits for the displayed week and day in Gantt Chart Light Library?

The work schedule and visible time limits can be set up using these properties:

Working|Week|Start
Visible|Day |Finish

Any combination of the columns above is permitted, generating properties such as WorkingWeekStart, WorkingWeekFinish, WorkingDayStart, ..., VisibleDayFinish (8 properties).

In addition, there is a NonWorkingIntervals collection which defines supplemental grayed out time intervals (but visible, if they are within the visible limits).