Creates and inserts partial copies of the standard started task items that have not yet been fully completed considering their remaining work effort into the managed hierarchy, and updates the finish date and times of the original task items to their completion points.
Used as preparation for rescheduling the remaining work effort task items, such as before calling the LevelResources()()() method.
Namespace:
DlhSoft.Windows.ControlsAssembly: DlhSoft.ProjectData.GanttChart.LightWPF.Controls (in DlhSoft.ProjectData.GanttChart.LightWPF.Controls.dll)
Syntax
C# |
---|
public ReadOnlyCollection<GanttChartItem> SplitAllRemainingWork( string remainingSuffix, string completedSuffix ) |
Visual Basic (Declaration) |
---|
Public Function SplitAllRemainingWork ( _ remainingSuffix As String, _ completedSuffix As String _ ) As ReadOnlyCollection(Of GanttChartItem) |
Parameters
- remainingSuffix
- Type: System..::.String
The suffix to apply to the Content property value for the new remaining work items.
- completedSuffix
- Type: System..::.String
The suffix to apply to the Content property value for the original items.